Court Facilities | Reassessment of Trial Court Capital-Outlay Projects (Action Required)
body
Summary
Summary
In June 2018, the Legislature attached specific trailer bill language
(section 8 of Sen. Bill 847) to the 2018 Budget Act, which required
that the Judicial Council conduct a reassessment of all trial court
capital-outlay projects that had not been fully funded up to and through
the 2018 Budget Act (FY 2018-19). This reassessment is due by
December 31, 2019, to two legislative committees. To complete this
reassessment, the Court Facilities Advisory Committee recommends
the Judicial Council update its current prioritization methodology, which
was last revised in 2008, by adopting the Revision of Prioritization
Methodology for Trial Court Capital-Outlay Projects and resultant
Statewide List of Trial Court Capital Projects prioritized on
needs-based/cost-based scores.
body
Recommendation
Recommendation
The Court Facilities Advisory Committee recommends that the Judicial Council, effective November 14, 2019, take the following actions:
1. Adopt the Revision of Prioritization Methodology for Trial Court Capital-Outlay Projects (see Attachment A).
2. Adopt the Statewide List of Trial Court Capital Projects (see Attachment B).
3. Delegate to the Administrative Director the authority to make technical changes to the reports for submission to the Legislature, subject to the review and approval of the CFAC chair and vice-chair.
body
Speakers
Speakers
Hon. Brad R. Hill, Chair, Court Facilities Advisory Committee
Hon. Steven Jahr (Ret.), Court Facilities Advisory Committee