Title: Court Facilities: Scope, Budget, and Schedule Approval for Downtown Sacramento Capital Project (Action Required)
Attachments: 1. 20160226-16-029.pdf

Title

Title

Court Facilities: Scope, Budget, and Schedule Approval for Downtown Sacramento Capital Project (Action Required)

 

body

Summary

Summary

The Court Facilities Advisory Committee (CFAC) recommended approving the scope, budget, and schedule for a new 53-courtroom courthouse in downtown Sacramento. This approval is predicated on two future conditions: the Judicial Council would not commit to move the project into Construction until construction-funding legislation has been enacted, and at the completion of construction, the Judicial Council will dispose of the vacated Gordon D. Schaber Courthouse property. To the benefit of all county residents, this project will consolidate facilities including replacement of the Schaber Courthouse, and provide a modern, secure courthouse in downtown Sacramento for criminal and civil calendars and operations.

 

body

Recommendation

Recommendation

The Court Facilities Advisory Committee recommended that the Judicial Council, effective February 26, 2016, approve the scope, budget, and schedule for a new 53-courtroom courthouse in downtown Sacramento, predicated on two future conditions: the Judicial Council would not commit to moving the project into Construction until construction-funding legislation has been enacted and, at the completion of construction, the Judicial Council will dispose of the vacated Gordon D. Schaber Courthouse property.